Huadian-Teninskaya Combined Cycle Power Plant Achieves Two Key Milestones in One Day
Time:September 02 2016

On August 30 Russian local time, two key milestones, i.e. successful energization of start-up standby transformer at one attemptand covering of turbine low-pressure cylinder were achieved on the same day.

 

At 18:03 local time, power transmission of start-up standby transformer and standby section of 6kV busbar was achieved through joint efforts of Chinese and Russian construction companies. At present, the standby section as well all system equipment and meters are operating properly with reliable and accurate readings, signals and monitor displays. Power transmission of the start-up standby transformer has been completed successfully.

 

At 23:30 local time, covering of turbine low-pressure cylinder was achieved. The Project adopts double-cylinder, impulse, dual pressure, extraction condensing turbine. The turbine has a primary adjustable steam extraction with an extraction pressure of 0.40MPa.

  • Add: Room 2802, harbour centre, 25 harbour road, wanchai, Hong Kong
  • Tel: +852-28104588
  • Fax: +852-28104566
  • Add: NO.2,Xuanwumennei Street ,Xicheng District,BeiJing
  • Tel: +8610-83567666
  • Fax: +8610-66088571

China Huadian HongKong Company Limited. All rights reserved